What would you do if a contractor underestimated the cost of job?
My heat pump guy is almost done, gave us a written estimate that we signed and sealed.
Then the cost of one particular material was 2x the estimated cost. He said this is cutting into estimate.
He is trying to not finish up the job like he wrote in the contract. The material was estimated $20/part, instead it was $40/part.
Should we be expected to cover it? Should we just make him finish it?
My heat pump guy is almost done, gave us a written estimate that we signed and sealed.
Then the cost of one particular material was 2x the estimated cost. He said this is cutting into estimate.
He is trying to not finish up the job like he wrote in the contract. The material was estimated $20/part, instead it was $40/part.
Should we be expected to cover it? Should we just make him finish it?

Comment